Mendota Elementary School

Thanks to the support of voters, Mendota Elementary School is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.

UPDATE FOR AUGUST 13, 2019


Completed for the week ending August 9, 2019

  • Project is in Construction Documents phase.  
  • Weekly Design Consultants meetings being held at LSE.
  • ICS walked the school to verify existing conditions of the school.


BUILDING PROJECTS

Academic and Program Improvements
Rightsize kindergarten classrooms to meet state guidelines
Handicapped accessibility improvements
Build additions for grades 1-4 classrooms and renovate existing space for collaboration/small-group commons
Addition of staff and visitor bathrooms
Lab renovations

Building Maintenance Improvements
Site improvements include concrete walks and paving
Exterior improvements include roofing, tuck pointing, and sealants
Interior finishes include flooring, stage partition, and gym equipment
Electrical improvements include lighting



PROJECT TIMELINE
Design and Planning: March 2019-September 2019 Construction Phase: April 2020-August 2020
Construction - Exterior Additions: Last Spring-Summer 2020
Construction - Interior Renovations: Summer 2020
Completion: Late August 2020