Heritage E-STEM Magnet School

Thanks to the support of voters, Heritage E-STEM Magnet School is in the process of making renovations and repairs to its facility. We will update this page weekly as construction progresses.

UPDATE FOR AUGUST 13, 2019

Completed for week ending August 9, 2019
  • Project is in design development phase.
  • Weekly design meetings are being held at LSE Architects. 
  • Input for design of the existing pool area is being gathered from stakeholders.




BUILDING PROJECTS

Academic and Program Improvements
Cafeteria handicapped accessibility improvements and removal of stage
Commons area access improvements and renovations
Music area improvements
Media production lab renovations
Meeting space renovation
Addition/renovation of relocated performance/multi-purpose space with stage

Building Maintenance Improvements
Site improvements include landscape, concrete walks, and fencing
Exterior improvements include tuck pointing, sealants, soffit venting, and door hardware
Interior finishes include doors, locker room lockers, elevator improvements, flooring and gym equipment
Mechanical improvements include boiler and chiller plants, piping, and ventilation
Electrical improvements include lighting and PA system



PROJECT TIMELINE
Design and Planning: March 2019-November 2019 Construction Phase: June 2020-August 2021
Construction - Interior Renovations: Summer 2020, 2021
Completion: Late August 2021



CONCEPT DRAWING